Muller road services upgrade

Share this page

Sharing...

Muller road services upgrade

  • Date 1:28 PM Wednesday 24 February 2021
  • Type Water Works

The initial works to locate the existing underground services from Redwood to Scott has been completed. The water main works is on schedule and started on the 22nd of Feb at the Redwood Street end.

Traffic detours will be in place starting on the 1st of March for the water works to continue, there will be no access to Muller Rd from Scott St entrance from this date for a period of approx. 3-4 weeks. Residents will have access to their properties from the Redwood St end only.

The major storm water and sewer works are scheduled to start early April 2021.

Appropriate measures will be taken to keep noise, dust and other environmental factors and restricted access to a minimum.

Council apologises for any inconvenience these works cause.