Awatere Valley Road – Road Closure
Update: 12 November 2026
As part of the Marlborough Roads Recovery, crews continue work at Cam Corner on Awatere Valley Road, 10.5km up the valley from Jordan Bridge to undertake repairs and reinstate the road.
Last week, sluicing from a helicopter successfully removed a significant amount of unstable material on the slope face following substantial earthworks at this site with over 22,000m3 of material having been removed. Further works have been undertaken this week, alongside geotechnical inspections, to assess slope stability and inform the next stages of works.
From 4pm on Friday 13 November, the status of Awatere Valley Road will move to open for all traffic.
The road status changing is weather permitting and subject to final inspections.
Works will continue under daytime construction closures to complete road reinstatement at this site.
These construction closures will be in place on weekdays at the following times:
- Mondays to Fridays, from 8am to 4.30pm, with openings on the hour every hour.
Outside of these closures the road will remain open to the public, including during the weekend.
The site will continue to be monitored and in the event of heavy rainfall or if it is deemed unsafe, the road will be closed until it is safe to re-open it.
Works may occur outside of these days and times under stop/go traffic management with delays of up to 15 minutes.
All work is subject to weather and other unforeseen circumstances. If the closure timings should change, an Antenno will be sent.
Emergency services will always be accommodated.
----------
Update: 4 November 2026
Caution: sluicing on Awatere Valley Road
On Thursday 5 November, sluicing is being undertaken on Awatere Valley Road at Cam Corner to remove unstable material from a slip face.
As this operation will cause a falling material hazard members of the public are advised to avoid the area completely for their own safety.
From 6am on Thursday gates on either side of the site will be locked while these works are undertaken.
The status of the road remains closed to all traffic. A date for the road opening will be notified as soon as the information is available.
----------
Update: 30 October 2026
Falling material hazard at Cam Corner.
Please avoid Awatere Valley Road at Cam Corner. Material is being sluiced from an unstable slope face on Saturday 31 October.
From 8am tomorrow gates on either side of the site will be locked while these works are undertaken.
Members of the public are advised to avoid the area completely for their own safety.
The road remains closed to all traffic
- - -
Update: 28 October
Awatere Valley Road at Cam Corner, 10.5km up the valley from Jordan Bridge, remains closed to all traffic.
Due to forecast weather conditions delaying works, Awatere Valley Road at Cam Corner will remain closed through the Marlborough Anniversary long weekend.
As the unstable material is unable to be reached from the ground, it will be removed by sluicing from a helicopter. Saturday 31 October is the earliest that conditions are settled enough for this work to commence. Following sluicing, crews will need to complete stabilisation works and specialist inspections before the road is opened.
Once the status of the road is open works will continue at the site under daytime construction closures on working days from 8am to 12pm and 12.30pm to 4.30pm to complete excavation, undertake drainage improvements and reinstate the road.
The road will open for residents and essential service travel from 12pm to 12.30pm.
A date for the road opening, and the start of construction closures will be notified as soon as they are available.
Public wishing to access Molesworth Station will need to do so from the Hanmer end.
There will be no access via Awatere Valley.
The site will continue to be monitored and in the event of heavy rainfall or if it is deemed unsafe, the road will be closed until it is safe to re-open it.
- - -
Update: 22 October 2026
Awatere Valley Road at Cam Corner, 10.5km up the valley from Jordan Bridge, will remain closed to all traffic.
Following rain delays, works continue to clear the large slip, stabilise the embankment and reinstate the road at Cam Corner. This work will continue into next week.
Once the remaining material has been excavated and specialist inspections undertaken, the road will open for the Marlborough Anniversary long weekend (weather permitting).
Works will continue at Cam Corner from 8am on Tuesday 3 November under construction closures to complete excavation, undertake drainage improvements and reinstate the road. It is expected over 22,000m3 of material will have been moved from the site once works are complete.
The construction closures will be in place until late November from 8am to 12pm and 12.30pm to 4.30pm.
The road will open for residents and essential service travel from 12pm to 12.30pm.
The site will continue to be monitored and in the event of heavy rainfall or if it is deemed unsafe, the road will be closed until it is safe to re-open it.
Emergency services will always be accommodated.
- - -
Awatere Valley Road at Cam Corner, 10.5km up the valley from Jordan Bridge, remains closed to all traffic.
Following further heavy rain, geotechnical inspections have identified further instability in the upper slope above the bridge. A large crack has developed, and the slip is actively moving. Crews continue working to remove the estimated 3000m3 of additional material at the top of the slope to stabilise the corner. Over 15,000m3 of material has already been moved from this site.
The road status of Awatere Valley Road at Cam Corner, remains closed until at least 23 October.
Public wishing to access Molesworth Station will need to do so from the Hanmer end.
There will be no access via Awatere Valley.